Friday, February 25, 2011

The beginnings of the Structure

Installing the posts that form part of the structure are next on the hit list as the decking boards will need to fit around them.

Footings are poured for the 2 posts that are in the garden beds



The posts are secured in the stirrups



Then the overhead beams are added, as the sleepers are all a standard 2.4m long the joins are strengthened with the metal plates that were custom made for a perfect fit.








The remaining beams are to be fixed later